The Approve for production task is added to the stage before production. Use this task if you want a user to approve application changes before those changes are send to production.

Do the following steps:
  1. Click the Info icon.
  2. In the Job name field, enter a name for the task.
  3. In the Assign to field, press the Down arrow key and select the user who approves the application for production. An email is sent to this user, who can approve or reject application changes from within the email.
  4. Click Submit.
  5. Continue configuring your pipeline. For more information, see one of the following topics:
Did you find this content helpful? YesNo

Have a question? Get answers now.

Visit the Support Center to ask questions, engage in discussions, share ideas, and help others.

We'd prefer it if you saw us at our best.

Pega.com is not optimized for Internet Explorer. For the optimal experience, please use:

Close Deprecation Notice
Contact us